Can secondary analysis run on MiSeq while a run is in progress?
Last updated
Was this helpful?
It is not possible to perform secondary analysis on the MiSeq when a sequencing run is in progress.
If a new sequencing run is started on the MiSeq before the secondary analysis of a previous run is complete, the secondary analysis is stopped automatically.
MiSeq computing resources are dedicated to either sequencing or analysis, and the system is designed in such a way that a sequencing command overrides an analysis command.
Secondary analysis can be requeued from MiSeq Reporter or Local Run Manager, when sequencing is not in progress.